Trenching Hazards & Controls

Review the key hazards, consequences and control measures for Trenching in a structured professional HSE format.

01
Hazard

Trench wall collapse

Potential Consequence

Crushing, suffocation or fatality

Persons at Risk

Workers inside the trench

Existing Controls

Suitable sloping, shoring or trench box and competent-person inspection

Additional Controls

Reassess when soil, water or vibration conditions change

02
Hazard

Contact with underground utilities

Potential Consequence

Electric shock, fire, gas or water release

Persons at Risk

Excavation crew

Existing Controls

Utility locating, drawings and controlled excavation method

Additional Controls

Restrict mechanical excavation near critical services

03
Hazard

Unsafe access and egress

Potential Consequence

Fall or delayed emergency evacuation

Persons at Risk

Workers inside the trench

Existing Controls

Suitable ladder or designed access point

Additional Controls

Check access suitability as work progresses

04
Hazard

Spoil pile too close to trench edge

Potential Consequence

Edge collapse or material falling into trench

Persons at Risk

Workers inside trench

Existing Controls

Safe spoil setback and area control

Additional Controls

Maintain excavated material at a safe distance from the trench edge

05
Hazard

Water accumulation in trench

Potential Consequence

Ground instability or drowning

Persons at Risk

Trench workers

Existing Controls

Drainage and pumping

Additional Controls

Stop work and reassess if uncontrolled water enters

06
Hazard

Heavy equipment loading near trench

Potential Consequence

Trench wall collapse

Persons at Risk

Workers inside trench

Existing Controls

Vehicle stand-off distance and traffic control

Additional Controls

Assess surcharge loading from heavy equipment against ground conditions

07
Hazard

Vehicle vibration near trench edge

Potential Consequence

Loss of trench wall stability

Persons at Risk

Workers inside trench

Existing Controls

Vehicle stand-off distance and area control

Additional Controls

Route heavy vehicle traffic at a safe distance from trench edges

08
Hazard

Damage to trench support system

Potential Consequence

Collapse or serious injury

Persons at Risk

Trench workers

Existing Controls

Shoring inspection and competent-person checks

Additional Controls

Reinspect support systems each shift and after adverse weather

09
Hazard

Lack of safe trench access

Potential Consequence

Trip, fall or delayed emergency escape

Persons at Risk

Trench workers

Existing Controls

Suitable ladder or access point

Additional Controls

Provide access points at suitable intervals along the work area

Related Risk Assessments

More from Excavation

Explore related activities, hazards and control measures from the same HSE risk category.

Explore Risk Library →
SERNEM

Turn this into your project risk assessment

Use these ready hazards as your starting point, customize controls, evaluate risk levels and prepare your project-specific assessment in SERNEM.

Start Risk Assessment
SERNEM
Trenching RISK ASSESSMENT
SRN-HIRARC
Revision: 1.0
ACTIVITYTrenchingCATEGORYExcavation
#ActivityHazardConsequencePersons at RiskExisting Risk ControlLSRiskAction Required / Additional ControlsPerson in ChargeDue DateRLRSResidual Risk
01TrenchingTrench wall collapseCrushing, suffocation or fatalityWorkers inside the trenchSuitable sloping, shoring or trench box and competent-person inspection3515
High
Reassess when soil, water or vibration conditions change--224
Low
02TrenchingContact with underground utilitiesElectric shock, fire, gas or water releaseExcavation crewUtility locating, drawings and controlled excavation method3412
High
Restrict mechanical excavation near critical services--224
Low
03TrenchingUnsafe access and egressFall or delayed emergency evacuationWorkers inside the trenchSuitable ladder or designed access point236
Medium
Check access suitability as work progresses--122
Low
04TrenchingSpoil pile too close to trench edgeEdge collapse or material falling into trenchWorkers inside trenchSafe spoil setback and area control339
Medium
Maintain excavated material at a safe distance from the trench edge--122
Low
05TrenchingWater accumulation in trenchGround instability or drowningTrench workersDrainage and pumping236
Medium
Stop work and reassess if uncontrolled water enters--122
Low
06TrenchingHeavy equipment loading near trenchTrench wall collapseWorkers inside trenchVehicle stand-off distance and traffic control339
Medium
Assess surcharge loading from heavy equipment against ground conditions--122
Low
07TrenchingVehicle vibration near trench edgeLoss of trench wall stabilityWorkers inside trenchVehicle stand-off distance and area control236
Medium
Route heavy vehicle traffic at a safe distance from trench edges--122
Low
08TrenchingDamage to trench support systemCollapse or serious injuryTrench workersShoring inspection and competent-person checks3412
High
Reinspect support systems each shift and after adverse weather--224
Low
09TrenchingLack of safe trench accessTrip, fall or delayed emergency escapeTrench workersSuitable ladder or access point236
Medium
Provide access points at suitable intervals along the work area--122
Low
Prepared By
Name / Signature / Date
Reviewed By
Name / Signature / Date
Approved By
Name / Signature / Date
SERNEM • Professional Risk AssessmentWork should not begin until required controls are implemented.