SILICA DUST CONTROL DURING CONCRETE CUTTING TOOLBOX TALK
Control respirable crystalline silica at source.
Preview is public. A free SERNEM account is required to download the standard PDF.
Toolbox Topic
SILICA DUST CONTROL DURING CONCRETE CUTTING TOOLBOX TALK
Duration
8–10 MINUTES
Date
Site / Area
Supervisor
Company
Participants
Document No
OBJECTIVE
Reduce exposure to respirable crystalline silica when cutting concrete, stone and masonry.
TOPIC EXPLANATION
Concrete, brick and stone cutting can release fine silica dust that is difficult to see. Breathing this dust can cause severe lung disease.
Where practical, use pre-cut materials, wet cutting or suitable on-tool extraction to control dust at source.
Apply task-assessed respiratory protection, fit checks, segregation and safe cleaning where engineering controls are insufficient.
REALISTIC SITE SCENARIO
A crew dry-cut concrete in an enclosed area.
Fine dust spread to nearby workers without adequate protection.
Water suppression, extraction, segregation and suitable respirators would have reduced exposure.
REMEMBER
Invisible dust can still be hazardous. Control silica at its source.
KEY HAZARDS
Breathing respirable silica.
Dust accumulating indoors.
Exposure of neighbouring workers.
Dust raised by dry sweeping.
Incorrect respiratory protection.
Slips on wet cutting slurry.
Water contacting electrical tools.
Injury from a cutting blade.
CONTROL MEASURES
Choose a lower-dust method.
Use water suppression or suitable extraction.
Inspect cutting equipment before use.
Segregate the work area.
Maintain extraction filters.
Assess required respirators.
Confirm correct respirator fit.
Avoid dry sweeping and compressed air.
Control wet surfaces and electrical risks.
Collect dust and slurry safely.
SUPERVISOR TALKING SCRIPT
Silica dust may be harmful even when it cannot be seen. We will control it using wet methods or extraction, segregate the area and use suitable respiratory protection.
DISCUSSION QUESTIONS
What material are we cutting?
How is dust suppressed?
Are neighbouring crews protected?
Is the respirator suitable?
How will waste be removed?
PRE-WORK VERIFICATION
Material assessed
Method selected
Dust controls ready
Tools checked
Area segregated
Filters suitable
Respirator selected
Fit confirmed
Water/electric risk checked
Waste plan ready
ATTENDANCE AND APPROVAL
Project / Site
Date
Presented by
Work area
Attendance and Signature
| # | Name | Position | Signature |
|---|---|---|---|
| 1 | |||
| 2 | |||
| 3 | |||
| 4 | |||
| 5 | |||
| 6 | |||
| 7 | |||
| 8 | |||
| 9 | |||
| 10 | |||
| 11 | |||
| 12 |
Supervisor Signature
HSE Approval
SERNEM HSE Resource — Approved site procedure, risk assessment, manufacturer instructions and local regulations take priority.