| 01 | Nitrogen Purging and Inerting | Oxygen displacement by nitrogen | Asphyxiation or fatality | Operators and nearby personnel | Approved purge plan, controlled access and oxygen monitoring | 2 | 5 | 10 High | Assess oxygen deficiency at vents and adjacent areas; verify suitable alarms and evacuation arrangements | - | - | 2 | 5 | 10 High |
| 02 | Nitrogen Purging and Inerting | Nitrogen accumulation in enclosed spaces | Loss of consciousness and fatality | Operators and nearby personnel | Confined-space permit system and isolation | 2 | 5 | 10 High | Prohibit routine entry into inerted spaces; plan rescue with trained personnel and suitable supplied breathing air | - | - | 2 | 5 | 10 High |
| 03 | Nitrogen Purging and Inerting | Exceeding pressure limits | Line or connection failure | Operators and nearby personnel | Approved pressure limits and suitable regulation | 2 | 3 | 6 Medium | Have competent personnel verify pressure indication, relief capacity and connection suitability | - | - | 2 | 3 | 6 Medium |
| 04 | Nitrogen Purging and Inerting | Hose connection separation | Hose whip and impact injury | Operators and nearby personnel | Pressure-rated hoses and connections | 2 | 3 | 6 Medium | Verify connection restraint; do not disconnect before depressurization | - | - | 2 | 3 | 6 Medium |
| 05 | Nitrogen Purging and Inerting | Incorrect line or open connection | Uncontrolled gas release | Operators and nearby personnel | Current P&ID and isolation plan | 3 | 3 | 9 Medium | Independently verify boundaries and record changes during shift handover | - | - | 3 | 3 | 9 Medium |
| 06 | Nitrogen Purging and Inerting | Noise at discharge point | Hearing damage | Operators and nearby personnel | Noise assessment and access restriction | 2 | 3 | 6 Medium | Specify hearing protection and safe discharge location based on assessment | - | - | 2 | 3 | 6 Medium |