Pinch point between flanges
Hand crushing
Work crew and affected nearby teams
Suitable alignment tool
Keep hands clear of the closing gap
Review the critical hazards, potential consequences, persons at risk and recommended control measures for Flange Alignment in one professional HSE workspace.
Review the key hazards, consequences and control measures for Flange Alignment in a structured professional HSE format.
Hand crushing
Work crew and affected nearby teams
Suitable alignment tool
Keep hands clear of the closing gap
Sudden movement and impact
Work crew and affected nearby teams
Pipe support and engineering review
Verify strain and support arrangements before alignment
Equipment and joint damage
Work crew and affected nearby teams
Approved assembly tolerance
Do not force unacceptable alignment using bolts
Tool projection and injury
Work crew and affected nearby teams
Manufacturer instructions and pre-use inspection
Verify tool capacity and seating surfaces
Falling section and crushing
Work crew and affected nearby teams
Approved temporary supports
Do not remove supports before the connection is complete
Hazardous material release
Work crew and affected nearby teams
Permit and isolation
Verify zero energy before routine alignment
Explore related activities, hazards and control measures from the same HSE risk category.
Use these ready hazards as your starting point, customize controls, evaluate risk levels and prepare your project-specific assessment in SERNEM.
Start Risk Assessment| ACTIVITY | Flange Alignment | CATEGORY | Mechanical Work |
| # | Activity | Hazard | Consequence | Persons at Risk | Existing Risk Control | L | S | Risk | Action Required / Additional Controls | Person in Charge | Due Date | RL | RS | Residual Risk |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | Flange Alignment | Pinch point between flanges | Hand crushing | Work crew and affected nearby teams | Suitable alignment tool | 3 | 4 | 12 High | Keep hands clear of the closing gap | - | - | 3 | 4 | 12 High |
| 02 | Flange Alignment | Release of pipe strain | Sudden movement and impact | Work crew and affected nearby teams | Pipe support and engineering review | 2 | 3 | 6 Medium | Verify strain and support arrangements before alignment | - | - | 2 | 3 | 6 Medium |
| 03 | Flange Alignment | Excessive alignment force | Equipment and joint damage | Work crew and affected nearby teams | Approved assembly tolerance | 2 | 3 | 6 Medium | Do not force unacceptable alignment using bolts | - | - | 2 | 3 | 6 Medium |
| 04 | Flange Alignment | Alignment tool slipping | Tool projection and injury | Work crew and affected nearby teams | Manufacturer instructions and pre-use inspection | 2 | 3 | 6 Medium | Verify tool capacity and seating surfaces | - | - | 2 | 3 | 6 Medium |
| 05 | Flange Alignment | Unsupported pipe section | Falling section and crushing | Work crew and affected nearby teams | Approved temporary supports | 3 | 4 | 12 High | Do not remove supports before the connection is complete | - | - | 3 | 4 | 12 High |
| 06 | Flange Alignment | Alignment on pressurized system | Hazardous material release | Work crew and affected nearby teams | Permit and isolation | 3 | 3 | 9 Medium | Verify zero energy before routine alignment | - | - | 3 | 3 | 9 Medium |