Free • TR / EN • Printable
LOTO Energy Isolation Verification Checklist
Before servicing, document each energy source, the authorized person's isolation method, lock and tag accountability, stored-energy controls and proof of zero energy.
How to use this worksheet
- Identify the exact machine, maintenance task and affected workers.
- Map electrical, pressure, mechanical, hydraulic, pneumatic, gravity and other energy sources.
- Have authorized personnel follow the approved shutdown, physical isolation and personal lock/tag procedure.
- Relieve or restrain stored energy and verify isolation through an appropriate safe test before work.
- Follow the employer's controlled lock transfer, shift handover and return-to-service procedure when circumstances change.
Worked field example
Example — Pump repair: Isolate and lock the motor supply, depressurize the line, prevent rotor movement, and have an authorized worker verify the de-energized state before service.
SERNEM — FIELD WORKSHEET
LOTO Energy Isolation Verification Checklist
Adapt this worksheet to actual site conditions.
Equipment and responsibilities
Energy isolation point register
| Energy source / point | Isolation and lock method | Verification / result | Authorized person |
|---|---|---|---|
Verification and release
This worksheet does not perform an isolation, prove a safe state, or authorize work. Follow the applicable energy-control standard and your employer's written procedure.
Frequently asked questions
Is a tag alone enough?
A tag is not automatically equivalent to a lock on a lockable isolator; verify the applicable legal criteria and supplementary protection.
When is isolation verified?
An authorized worker verifies effective isolation after applying controls and before servicing starts.