1
Equipment & Electrical
Temporary Power Inspection Checklist
Temporary distribution and site power controls.
0/16
0%
Live safety status
WARNING
Complete all applicable items.
Progress
0%
Compliance
0%
Total questions
16
Answered
0
Findings
0
Critical findings
0
Temporary Power Controls
2
Circuits have appropriate overcurrent and residual-current protection.
Critical3
Cables are routed, supported and protected from traffic and water.
4
Connections, plugs and sockets are enclosed and undamaged.
5
Isolation and emergency shut-off points are labelled and accessible.
6
Generators are grounded, ventilated and safely refuelled.
7
Only authorized persons make or modify connections.
8
Periodic inspection and test records are available.
Management, Emergency and Closeout
9
The task-specific risk assessment and method statement are current and available.
10
Workers and supervisors are competent, briefed and authorized for the activity.
11
Required PPE and task-specific protective equipment are available and used.
12
Emergency arrangements, contacts and access routes are known and available.
13
The work area is controlled against unauthorized access and changing conditions.
14
Relevant records, inspections, permits or certificates are current and traceable.
15
Changes in scope, people, equipment or conditions are reviewed before work continues.
16
Findings have an assigned owner, target date and closeout verification.
Inspection result
Calculated live from the inspection responses.
Inspection incomplete
Yes: 0No: 0N/A: 0