OBJECTIVE

✓

Prevent shock, arc events, unexpected energisation and equipment damage during initial electrical commissioning.

TOPIC EXPLANATION

✓

First energisation is more than operating a breaker. Authorised staff must verify test records, circuit boundaries, equipment condition and temporary connections.

✓

The energisation sequence, roles, communication and stop method must be approved in advance. Keep unauthorised personnel outside controlled areas.

✓

Once power is applied, the system status changes. Update permits, warning notices and access rules to match the energised condition.

REALISTIC SITE SCENARIO

✓

A newly installed panel was scheduled for energisation without notifying adjacent contractors.

✓

A worker approached an open cable compartment and risked contact with live parts.

✓

Shared notification, access control and verified boundaries would have reduced the risk.

REMEMBER

✓

First energisation must only follow an approved procedure led by authorised electrical personnel.

KEY HAZARDS

✓

Unexpected exposure to live voltage.

✓

Contact with open terminals.

✓

Arc flash and burns.

✓

Energising the wrong circuit.

✓

Unprotected temporary wiring.

✓

Other crews unaware of the change.

✓

Incorrect phasing or test connections.

✓

Unknown emergency shutdown method.

CONTROL MEASURES

✓

Verify the approved energisation plan.

✓

Nominate qualified electrical personnel.

✓

Complete required test and inspection records.

✓

Confirm circuits, boundaries and labels.

✓

Inspect temporary leads and test connections.

✓

Secure covers and restrict access.

✓

Assess shock and arc flash protection.

✓

Notify adjacent crews and operations.

✓

Confirm emergency shutdown and contact.

✓

Document the post-energisation status.

SUPERVISOR TALKING SCRIPT

✓

Initial energisation is controlled by the authorised electrical team. We will confirm the circuit, area boundary and communication before power is applied. Everyone else stays clear.

DISCUSSION QUESTIONS

✓

Who authorises energisation?

✓

Which circuits will become live?

✓

Are tests documented?

✓

How is power isolated in an emergency?

✓

Have adjacent teams been told?

PRE-WORK VERIFICATION

✓

Plan authorised

✓

Qualified team assigned

✓

Tests complete

✓

Circuit boundary clear

✓

Labels checked

✓

Temporary leads checked

✓

Covers secured

✓

Access controlled

✓

Emergency method known

✓

Operations notified

ATTENDANCE AND APPROVAL

✓

Project / Site

✓

Date

✓

Presented by

✓

Work area

Attendance and Signature

#NamePositionSignature
1
2
3
4
5
6
7
8
9
10
11
12

Supervisor Signature

HSE Approval

SERNEM HSE Resource — Approved site procedure, risk assessment, manufacturer instructions and local regulations take priority.