Professional scaffold inspection

Scaffold Inspection Checklist

Inspect scaffold foundations, structural components, platforms, access and protective systems before releasing the scaffold for use.

Progress

0%

Compliance score

0%

Critical findings

0

Live safety status

WARNING

The inspection is incomplete. Complete all applicable items.

General Requirements

1

The scaffold has been erected, altered or dismantled only by trained and competent personnel.

Critical
2

A valid scaffold inspection tag is securely attached at the access point.

Critical
3

The scaffold inspection remains valid for the current date, shift and site requirements.

Critical
4

The scaffold is suitable for the intended work activity and required working height.

Critical
5

The scaffold load class or permitted loading is identified and understood.

6

The safe working load is displayed where required and has not been exceeded.

Critical
7

No unauthorized modification, removal or relocation of scaffold components is observed.

Critical

Foundation and Base

8

The supporting ground or structure is firm, stable and capable of carrying the scaffold load.

Critical
9

Base plates are installed beneath all scaffold standards.

Critical
10

Suitable sole boards are installed where required to distribute the load.

Critical
11

Adjustable base jacks are correctly installed and remain within their permitted extension.

Critical
12

No settlement, sinking, tilting or movement is visible at the scaffold base.

Critical
13

There is no standing water, erosion or loss of support around the scaffold foundation.

14

Excavation, vehicle movement or nearby work has not undermined the scaffold foundation.

Critical

Structural Components

15

Standards are vertical, correctly spaced and free from significant damage.

Critical
16

Ledgers are complete, level and securely connected.

Critical
17

Transoms and platform supports are correctly positioned and secured.

Critical
18

Couplers, clamps and connection devices are correctly installed and tightened.

Critical
19

Scaffold tubes and frames are free from cracks, severe corrosion, bending or deformation.

Critical
20

No standards, ledgers, transoms or other essential structural components are missing.

Critical
21

Scaffold components are compatible and have not been improvised with unsuitable materials.

Critical

Bracing, Ties and Stability

22

Facade or longitudinal bracing is installed in the required locations.

Critical
23

Cross bracing is complete, correctly connected and undamaged.

Critical
24

Plan or horizontal bracing is installed where required by the scaffold design.

Critical
25

Scaffold ties are installed at the required spacing and locations.

Critical
26

Anchors and tie points are secure, suitable and free from visible damage.

Critical
27

No scaffold tie, anchor or brace has been removed without authorization and replacement control.

Critical
28

Free-standing or mobile scaffold height and base dimensions remain within the approved limits.

Critical

Working Platforms

29

Working platforms are fully decked for the intended activity.

Critical
30

No dangerous gaps exist between platform units, the scaffold structure or the work face.

Critical
31

Platform boards and metal decks are free from cracks, severe damage, deformation or contamination.

Critical
32

Platform units are secured against movement, uplift or displacement.

Critical
33

The platform provides sufficient working width for workers, tools and materials.

34

Platform board overhang is controlled and does not create instability or a trip hazard.

35

Materials are distributed safely and the platform is not overloaded.

Critical
36

Platform openings, hatches and penetrations are closed or adequately protected.

Critical

Edge Protection

37

Top guardrails are installed on all exposed platform sides and ends.

Critical
38

Midrails or equivalent intermediate protection are installed.

Critical
39

Toe boards are installed and complete on exposed platform edges.

Critical
40

Platform ends, returns and access openings are adequately protected.

Critical
41

Guardrails and toe boards are secure and free from significant damage.

Critical
42

The gap between the working platform and structure is minimized or otherwise protected.

Critical

Access and Egress

43

A safe and designated means of access and egress is provided.

Critical
44

Access ladders or stair towers are installed inside the scaffold where practicable.

45

Access ladders are free from damage, contamination and missing rungs.

Critical
46

Access ladders are securely fixed against slipping or displacement.

Critical
47

Ladder landings and rest platforms are provided where required.

48

Self-closing gates or equivalent protection are installed at access openings.

Critical
49

Access routes, ladders, stairways and landings are unobstructed.

Critical
50

Workers are not required to climb scaffold frames, braces or guardrails.

Critical

Falling Object Protection

51

Tools and loose equipment are secured where they could fall from the scaffold.

Critical
52

Materials are stored away from platform edges and cannot roll or slide.

Critical
53

Debris netting, brick guards or equivalent protection are installed where required.

54

An exclusion zone is established below and around the scaffold where falling-object risk exists.

Critical
55

Barricades and warning signs are visible and suitable for the level of risk.

56

Simultaneous work above and below has been eliminated or properly controlled.

Critical

Electrical and Surrounding Hazards

57

Safe clearance is maintained from overhead lines and other energized equipment.

Critical
58

Temporary electrical cables are protected against damage and do not create trip hazards.

Critical
59

Lighting is sufficient for safe access, work and emergency evacuation.

60

The scaffold is protected from vehicle, crane and mobile-equipment impact.

Critical
61

Nearby process, pressure, heat, chemical and operational hazards have been controlled.

Critical

Housekeeping

62

Working platforms are free from unnecessary waste, loose materials and obstructions.

63

Access ways, ladders, stairs and landing areas are clean and clear.

Critical
64

Oil, mud, ice, water and other slip hazards have been removed or controlled.

Critical
65

No sharp edges, protruding tubes or exposed components create injury hazards.

66

Scaffold materials and work equipment are stored in an orderly and stable manner.

Weather and Environmental Conditions

67

Wind conditions are within the permitted limits for scaffold use.

Critical
68

Rain, snow and ice conditions have been evaluated and controlled.

Critical
69

Scaffold use has been stopped where lightning or severe weather creates unacceptable risk.

Critical
70

Visibility is sufficient for safe work and access.

71

Sheeting, netting and temporary coverings have not created excessive wind loading.

Critical

Mobile Scaffolds

72

Castors and wheels are suitable, undamaged and securely attached.

Critical
73

All wheel brakes are engaged before workers access or use the scaffold.

Critical
74

Outriggers or stabilizers are correctly installed where required.

Critical
75

The mobile scaffold is positioned on a level, firm and obstruction-free surface.

Critical
76

No person remains on the scaffold while it is being moved.

Critical

Final Inspection and Release

77

No unresolved critical defect remains before the scaffold is released for use.

Critical
78

Identified defects have been recorded, assigned and controlled.

Critical
79

The scaffold inspection tag has been updated to reflect the current status.

Critical
80

Unsafe or incomplete scaffolds are tagged, barricaded and prevented from use.

Critical
81

The scaffold is formally accepted and released for its intended use.

Critical

Inspection Summary

Live overview calculated automatically from the inspection responses.

Total questions

81

Answered

0

Yes answers

0

No answers

0

N/A answers

0

Completion

0%

Compliance

0%

Critical findings

0

Open actions

0

High / critical priority

0

Findings Summary

Corrective actions created from items answered No.

No findings recorded

Items answered No will automatically appear in this section.

Inspection result

Inspection incomplete

Answer every applicable item to complete the inspection.

Completed

0/81

Compliance score

0%

Critical findings

0