←Back to Dashboard
← Toolbox Library
SERNEM Toolbox● Ready8–10 MINUTES

LOAD LANDING AND SLING REMOVAL SAFETY TOOLBOX TALK

Prevent crushing while placing and unhooking suspended loads.

Load stability, supports, lowering signals and controlled hook release.

Checking account…
← Back to Toolbox Library

Preview is public. A free SERNEM account is required to download the standard PDF.

Toolbox Topic

LOAD LANDING AND SLING REMOVAL SAFETY TOOLBOX TALK

Duration

8–10 MINUTES

Date

Site / Area

Supervisor

Company

Participants

Document No

OBJECTIVE

✓

Prevent crushing, load tipping and pinch injuries while lowering, supporting and removing lifting accessories from loads.

TOPIC EXPLANATION

✓

A load may remain unstable after it touches the ground or a support. Centre of gravity, slope, chocks and support capacity must be planned.

✓

Removing or loosening rigging while the load is partly suspended or not reliably supported can trigger sudden movement.

✓

Use one clear signalling arrangement and keep hands away from the interface between the load and its landing supports.

REALISTIC SITE SCENARIO

✓

A team lowered a heavy pipe spool onto a steel cradle and began releasing rigging too early.

✓

The spool rotated on the cradle, placing a nearby worker's fingers in a potential pinch zone.

✓

Suitable chocks, verified stability and waiting until sling tension was fully removed would have controlled the event.

REMEMBER

✓

Never release rigging until the load is stable and supported; keep hands clear of landing and crush zones.

KEY HAZARDS

✓

Hand trapping between load and support.

✓

Overturning of landing stands or frames.

✓

Rolling or sliding load.

✓

Premature sling release.

✓

Recoil of hooks or lifting gear.

✓

Personnel beneath suspended loads.

✓

Insufficient chocks or supports.

✓

Loss of signals between rigger and operator.

CONTROL MEASURES

✓

Assess landing location and load centre of gravity.

✓

Confirm stand, chock and support capacity.

✓

Provide a stable clear landing area.

✓

Restrict access to the landing zone.

✓

Use the lifting-plan signalling arrangement.

✓

Keep hands and feet away from crushing interfaces.

✓

Lower slowly and verify stability.

✓

Never unhook before rigging is unloaded.

✓

Remove hooks and slings in a controlled sequence.

✓

Reassess rolling and sliding risks after landing.

SUPERVISOR TALKING SCRIPT

✓

The landing and unhooking phase is a critical part of every lift. Confirm the load is fully supported and cannot move. Nobody is to put hands or feet beneath the load.

DISCUSSION QUESTIONS

✓

Where will the load be supported?

✓

Could it roll or slide?

✓

Is it fully stable?

✓

Who releases the slings, and when?

✓

Who gives lowering commands?

PRE-WORK VERIFICATION

✓

Landing location ready

✓

Centre of gravity assessed

✓

Supports rated

✓

Chocks available

✓

Exclusion zone set

✓

Slinger identified

✓

Hands and feet clear

✓

Load stability verified

✓

Rigging tension removed

✓

Crew briefed

ATTENDANCE AND APPROVAL

✓

Project / Site

✓

Date

✓

Presented by

✓

Work area

Attendance and Signature

#NamePositionSignature
1
2
3
4
5
6
7
8
9
10
11
12

Supervisor Signature

HSE Approval

SERNEM HSE Resource — Task-specific risk assessment, authorised procedures, manufacturer instructions and local law take precedence.