Work at height · SERNEM
Grating Installation and Floor Opening Method Statement
Removing or replacing floor grating can immediately create a fall hazard. Secure barriers and an alternative access route before work starts.
Work sequence, hazards and safeguards
Illustrative sequence only: adapt to the approved job pack and site conditions.
- 1
Plan openings and access
- Hazard
- Unexpected opening and access demand
- Safeguard
- Confirm installation drawings, permit boundaries and alternative pedestrian routes.
- 2
Install collective protection
- Hazard
- Falls through edges or floor openings
- Safeguard
- Provide suitable engineered edge protection, secure covers or platforms before removal.
- 3
Manage handling and falling objects
- Hazard
- Dropped grating, hand injuries and persons below
- Safeguard
- Use competent personnel, suitable handling equipment, exclusion below and clear communications.
- 4
Install and verify fixings
- Hazard
- Displaced panels or premature loading
- Safeguard
- Have a competent person verify supports and fixings against drawings and manufacturer requirements.
- 5
Reopen walkway after acceptance
- Hazard
- Missing fasteners or uncontrolled access
- Safeguard
- Keep the area restricted until acceptance, opening checks and load suitability are verified.
Three critical pre-start verification points
- Alternative route and barriers ready before opening
- Lower-level access excluded and materials secured
- Fixings accepted by a competent person
Stop-work triggers
Stop for unprotected openings, uncontrolled dropped-object exposure, unsuitable platforms or missing fixings.
Frequently asked questions
Can barriers be removed as soon as panels are placed?
No. Access should remain restricted until supports, fixings and suitability are verified.
Is warning tape always adequate?
Tape alone should not be treated as effective fall prevention where a physical barrier or cover is required.
Official technical sources
These sources have jurisdiction-specific scope; verify local legal and engineering requirements.
Prepare your own document
Open the existing SERNEM generator to prepare and edit a site-specific method statement separately from this reference. Printing from the tool may require sign-in.
Open method statement generator →