Chain Hoist and Tirfor Lifting Method Statement Example
Manual lifting devices still require competent planning: anchor strength, load paths, rated capacity and unintended movement must be controlled.
Work sequence, hazards and safeguards
Illustrative sequence only: adapt to the approved job pack and site conditions.
- 1
Confirm load and lift plan
- Hazard
- Unknown centre of gravity and load characteristics
- Safeguard
- Have a competent person verify load information, lifting direction and planned sequence.
- 2
Verify anchors and equipment
- Hazard
- Unsuitable anchors, overload or equipment failure
- Safeguard
- Match approved anchor capacity, device identification and inspection records.
- 3
Establish exclusion and communication
- Hazard
- Working below load, trapping and load swing
- Safeguard
- Protect the load route, exclude bystanders and confirm operator/signaler roles.
- 4
Move load under competent supervision
- Hazard
- Sudden load movement or loss of control
- Safeguard
- Follow approved equipment instructions and halt for deformation, abnormal sound or loss of control.
- 5
Secure load and demobilize
- Hazard
- Unsupported load and uncontrolled removal
- Safeguard
- Confirm the load is safely supported independently before releasing rigging.
Three critical pre-start verification points
- Load, centre of gravity and anchor verified
- Hoist and rigging inspection records valid
- Nobody is positioned under the suspended load
Stop-work triggers
Stop for unknown anchor strength, unverified equipment ratings, suspected overload, persons below the load or uncontrolled movement.
Frequently asked questions
Can a chain hoist be attached to a scaffold?
Only where a purpose-designed attachment is verified for the loads by competent designers or manufacturer instructions; ordinary scaffold tubes are not automatically suitable anchors.
Does hand-operated lifting require planning?
Yes. Both powered and manually operated hoists require risk-appropriate competent planning.
Official technical sources
These sources have jurisdiction-specific scope; verify local legal and engineering requirements.
Prepare your own document
Open the existing SERNEM generator to prepare and edit a site-specific method statement separately from this reference. Printing from the tool may require sign-in.
Open method statement generator →